- SECTION 08405
-
- METAL-FRAMED CLAD ENTRANCES
- NOTE ** ACI Distribution metal framed clad entrances.
- NOTE **
- NOTE ** This section is based on products fabricated by ACI
- Distribution, which has locations at the following
- addresses:
- NOTE **
- NOTE ** West of Rocky Mountains:
- NOTE ** 9010 S. Norwalk Boulevard
- NOTE ** Santa Fe Springs CA 90670
- NOTE ** Tel: (800) 285-3677
- NOTE ** Tel: (562) 908-8893
- NOTE ** Fax: (562) 695-8496
- NOTE **
- NOTE ** East of Rocky Mountains:
- NOTE ** 129000 Nicholson Road
- NOTE ** Farmers Branch TX 75234
- NOTE ** Tel: (800) 284-4527
- NOTE ** Tel: (972) 484-3691
- NOTE ** Fax: (972) 247-6457.
- NOTE **
- NOTE ** ACI Distribution offers a variety of architectural
- building products, including tempered glass
- handrail assemblies, metal-framed clad entrances,
- and all-glass entrances.
- NOTE **
- NOTE ** SECTION 08405 - METAL FRAMED CLAD ENTRANCES,
- Copyright 1997, The Architect's Catalog, Inc.
-
-
- PART 1 GENERAL
-
- 1.1 SECTION INCLUDES
- NOTE ** Delete items below not required for project.
-
- A. Metal Framed Clad Entrances.
-
- 1.2 RELATED SECTIONS
- NOTE ** Delete any sections below not relevant to this
- project; add others as required.
- A. Section 08410 - Metal-Framed Storefronts.
-
- B. Section 08710 - Door Hardware.
-
- C. Section 08800 - Glazing.
-
- 1.3 REFERENCES
- NOTE ** Delete references from the list below that are not
- actually required by the text of the edited
- section.
-
- A. ASTM A 666 - Standard Specification for Austenitic
- Stainless Steel Sheet, Strip, Plate, and Flat Bar.
-
- B. ASTM B 455 - Standard Specification for Copper-Zinc-Lead
- (Leaded Brass) Extruded Shapes.
-
- C. NAAMM Metal Finishes Manual; National Association of
- Architectural Metal Manufacturers.
-
- 1.4 SUBMITTALS
-
- A. Submit under provisions of Section 01300.
-
- B. Product Data: Fabricator's descriptive literature for
- specified components.
-
- C. Shop Drawings: Dimensioned drawings as follows:
- 1. Plans: Indicate layout of entrance assemblies.
- 2. Elevations:
- a. Appearance of entrance layouts; include locations
- of visible seams in metal cladding.
- b. Locations and identification of manufacturer-
- supplied door hardware.
- c. Locations and sizes of cut-outs and drilled holes
- for other door hardware.
- 3. Details:
- a. Interface with adjacent construction; include
- requirements for support and bracing at openings.
- b. Cross-section profiles of metal members,
- including mullions, perimeter framing, and door
- stiles and rails; include cladding details and
- seam locations.
- c. Installation details.
- d. Appearance of fabricator-supplied door hardware.
- 4. Schedule: Listing of each type component in entrance
- assemblies, cross-referenced to shop drawing plans,
- elevations, and details.
- NOTE ** Delete the following paragraph if specifying custom
- colors or finishes, or if selections are specified
- in this section.
-
- D. Selection Samples: Two sets, representing fabricator's
- full range of available metal materials and finishes.
-
- E. Verification Samples: Two samples, minimum size 2 inches
- (50 mm) by 3 inches (76 mm), representing actual material
- and finish of sight-exposed metal.
-
- F. Quality Assurance Submittals: Contractor's certification
- that installer of entrance assemblies meets specified
- qualifications.
-
- G. Closeout Submittals: Operation and maintenance data for
- fabricator-supplied operating hardware.
-
-
- 1.5 QUALITY ASSURANCE
-
- A. Installer Qualifications: Minimum three (3) years
- installing entrance assemblies similar to that specified
- in this section.
- NOTE ** Delete the following paragraph if not required.
-
- B. Pre-Installation Meetings:
- 1. Convene at job site seven (7) calendar days prior to
- scheduled beginning of construction activities of
- this section to review requirements of this section.
- 2. Require attendance by representatives of the
- following:
- a. Installer of this section.
- b. Other entities directly affecting, or affected
- by, construction activities of this section.
- 3. Notify Architect four (4) calendar days in advance of
- scheduled meeting date.
-
- 1.6 DELIVERY, STORAGE, AND HANDLING
-
- A. Store products of this section in fabricator's unopened
- packaging until installation.
-
- 1.7 PROJECT CONDITIONS
-
- A. Field Measurements: When construction activities permit,
- take field measurements at locations to receive products
- of this section; note discrepancies on submitted shop
- drawings.
-
- 1.8 SCHEDULING
-
- A. Ensure that metal components to be clad, and templates
- for door hardware not supplied by fabricator, are
- available to fabricator of this section to allow
- construction activities to proceed in accordance with
- construction progress schedule.
-
-
- PART 2 PRODUCTS
-
- 2.1 COMPONENTS
- NOTE ** Retain one of the following three paragraphs;
- retain first if aluminum components are specified
- in another section (verify section number and
- coordinate within section), retain second if
- aluminum components profiles and sizes are
- indicated on drawings, retain third if specifying
- component profiles in this section (enter required
- information and delete items that do not apply).
-
- A. Stile and Rail Aluminum-Framed Glass Entrances:
- Specified in Section 08410; sizes indicated on drawings.
-
- B. Stile and Rail Aluminum-Framed Glass Entrances: Types
- and dimensions indicated on drawings.
-
- C. Stile and Rail Aluminum-Framed Glass Entrances:
- 1. Door size: __ feet __ inches (__ mm) width by __
- feet __ inches (__ mm) height by __ inch (__ mm)
- thickness.
- 2. Stile dimension: __ inches (__ mm).
- 3. Top rail dimension: __ inches (__ mm).
- 4. Center rail dimension: __ inches (__ mm).
- 5. Bottom rail dimension: __ inches (__ mm).
- 6. Glazing provisions: Flush stops, interior glazed.
- 7. Glazing provisions: Flush stops, exterior glazed.
- NOTE ** Retain one of the following three paragraphs;
- retain first if aluminum components are specified
- in another section (verify section number and
- coordinate within section), retain second if
- aluminum components profiles and sizes are
- indicated on drawings, retain third if specifying
- component profiles in this section (enter required
- information and delete items that do not apply.)
-
- D. Mullions: Specified in Section 08410; sizes and
- configurations indicated on drawings.
-
- E. Mullions: Types, configurations, and dimensions
- indicated on drawings.
-
- F. Mullions:
- 1. Configurations: Indicated on drawings
- 2. Cross-sectional dimensions: __ inches (__ mm) width
- by __ inches (__ mm) depth.
- 3. Glazing provisions: Flush stops, interior glazed.
- 4. Glazing provisions: Flush stops, exterior glazed.
- NOTE ** Retain one of the following paragraphs to specify
- glazing.
-
- G. Glazing: Specified in Section 08410, and as follows:
- 1. Doors: __ inch (__ mm) overall thickness.
- 2. Sidelites: __ inch (__ mm) overall thickness.
-
- H. Glazing: Specified in Section 08800, and as follows:
- 1. Doors: __ inch (__ mm) overall thickness.
- 2. Sidelites: __ inch (__ mm) overall thickness.
- NOTE ** Retain one of the following two paragraphs if
- specifying stainless steel or brass cladding;
- consult with fabricator for material specifications
- if other metal is specified. Coordinate with
- REFERENCES Article of PART 1 of this section.
-
- I. Cladding:
- 1. Material: Stainless steel conforming to ASTM A 666,
- Type 304; ___ inch (__ mm) minimum thickness.
- 2. Finish: Number 4, satin polish.
- 3. Finish: Number 8, mirror polish.
- NOTE ** Delete the above sub-paragraphs specifying finish
- and retain the following if specifying finish in
- accordance with NAAMM Metal Finishes Manual; delete
- if not required.
- 4. Finish: NAAMM designation ________________.
-
- J. Cladding:
- 1. Material: Brass conforming to ASTM B 455, UNS
- C28000; ___ inch (__ mm) minimum thickness.
- 2. Finish: Number 4, satin polish.
- 3. Finish: Number 8, mirror polish.
- 4. Finish: Satin oxidized oil rubbed finish.
- 5. Finish: clear baked enamel finish .
- NOTE ** Delete the above sub-paragraphs specifying finish
- and retain the following if specifying finish in
- accordance with NAAMM Metal Finishes Manual; delete
- if not required.
- 6. Finish: NAAMM designation ________________.
-
- NOTE ** Retain one of the following two paragraphs to
- specify door hardware; if specifying door hardware
- to be supplied by fabricator, consult fabricator
- for additional information and insert into second
- paragraph.
-
- K. Door Hardware: Specified in Section 08710.
-
- L. Door Hardware:
- 1. Supplied by fabricator as follows:
- a. Hinges: ___________________________.
- b. Closers: __________________________.
- c. Push/pulls: _______________________.
- d. Locksets: _________________________.
- e. Exit devices: _____________________.
- 2. Finish of sight-exposed metals: Matching finish of
- fittings.
- NOTE ** Delete the following sub-paragraph if all door
- hardware to be supplied by door manufacturer.
- 3. All other door hardware: Specified in Section 08710.
-
- 2.2 FABRICATION
-
- A. Acceptable Fabricator: ACI Distribution, located at one
- of the following addresses:
- 1. West of Rocky Mountains: 9010 S. Norwalk Boulevard,
- Santa Fe Springs CA 90670; ASD. Tel. (800) 285-3677
- or (562) 908-8893, Fax. (562) 695-8496.
- 2. East of Rocky Mountains: 129000 Nicholson Road,
- Farmers Branch TX 75234; ASD. Tel. (800) 284-4527 or
- (972) 484-3691, Fax. (972) 247-6457.
- NOTE ** Delete one of the two following paragraphs;
- coordinate with Division 1 requirements.
-
- B. Requests for substitution will be considered in
- accordance with provisions of Section 01600.
-
- C. Substitutions: Not permitted.
-
- D. Shop Assembly:
- 1. Clad aluminum components with specified cladding
- materials, forming flat surfaces and edges of
- cladding materials to fit tight to aluminum surfaces.
- 2. Locate seams in cladding materials in accordance with
- shop drawings, forming straight hairline-width butt
- joints.
- 3. Permanently laminate cladding materials to aluminum
- surfaces; visible fastening devices not permitted.
- 4. Prepare clad components for specified hardware.
- 5. Finish surfaces of cladding materials to specified
- finish; apply strippable protective materials to
- finished surfaces.
- 6. Assemble components to extent practical, considering
- shipping limitations.
-
-
- PART 3 EXECUTION
-
- 3.1 EXAMINATION
-
- A. Verify that openings to receive entrance assemblies are
- of correct size and are prepared correctly, in accordance
- with shop drawings.
-
- B. Installer's Examination:
- 1. Have installer of this section examine conditions
- under which construction activities of this section
- are to be performed, then submit written notification
- if such conditions are unacceptable.
- 2. Transmit two copies of installer's report to
- Architect within 24 hours of receipt.
- 3. Beginning construction activities of this section
- before unacceptable conditions have been corrected is
- prohibited.
- 4. Beginning construction activities of this section
- indicates installer's acceptance of conditions.
-
- 3.2 INSTALLATION
- NOTE ** Delete references to related construction
- activities of other sections that do not apply to
- project; add others as applicable to project.
- Coordinate with RELATED SECTIONS Article of PART 1
- of this section.
-
- A. Install entrance assembly components in accordance with
- shop drawings.
-
- B. Remove strippable protective materials from metal
- surfaces only to extent required for installation of
- assembly, and to receive glazing and door hardware.
- NOTE ** Retain one of the following two sub-paragraphs;
- retain first if requiring installer of this section
- to install glazing, retain second if all glazing is
- installed under Section 08800.
-
- C. Install glazing in accordance with installation
- requirements of Section 08800, and shop drawings.
-
- D. Installation of glazing is specified in Section 08800.
- NOTE ** Retain one or more of the following three sub-
- paragraphs; retain first if all door hardware is
- specified in Section 08710, retain second if
- requiring all or some door hardware on doors in
- this section to be installed by installer of this
- section, retain third if door hardware, other than
- supplied by door manufacturer, is specified in
- Section 08710.
-
- E. Installation of door hardware is specified in Section
- 08710.
-
- F. Install fabricator-supplied door hardware in accordance
- with installation requirements of Section 08710, shop
- drawings, and door hardware manufacturers' instructions.
-
- G. Installation of other door hardware is specified in
- Section 08710.
-
- H. Site Tolerances:
- 1. Variation from level, horizontal components and sight
- lines: 1/8 inch in 10 feet (3 mm in 3 m), non-
- cumulative.
- 2. Variation from plumb, vertical components and sight
- lines: 1/8 inch in 10 feet (3 mm in 3 m), non-
- cumulative.
- 3. Variation from plane, installed assembly: Maximum
- 1/16 inch (1.5 mm)
-
- 3.3 ADJUSTING
-
- A. Adjust entrance doors to swing correctly, without binding
- to frame, sill, or adjacent doors.
- NOTE ** Retain the following sub-paragraph if installation
- of door hardware is specified in this section.
-
- B. Adjust door hardware to operate correctly.
-
- 3.4 CLEANING
-
- A. Immediately prior to Substantial Completion, remove
- strippable protective materials from metal surfaces;
- clean metal surfaces free of adhesive residue and other
- foreign substances, using cleaning materials and methods
- recommended by fabricator of this section.
-
- 3.5 PROTECTION
-
- A. Protect finished installation from damage by subsequent
- construction activities until Substantial Completion.
-
- B. Repair components damaged by subsequent construction
- activities in accordance with fabricator's
- recommendations; replace damaged components that cannot
- be repaired to Architect's acceptance.
-
-
- END OF SECTION
-